PLANNING / INFORMATION

MAGNUS MECHANICAL  SCHEDULE

 ASSUMPTION: FOB submitted by M/s MDT, Magnus Material schedule 

1)   FABRICATION & ERECTION WORK OF DUCTING & STRUCTURES: (AUXILIARY BAY, MECHANICAL ANNEXURE, RADIATOR SUPPORTING STRUCTURE, CHIMNEY & ITS SUPPORTING STRUCTURE) SCHEDULE ATTACHED IN ANNEXURE  1.
  1. All structural Materials received at site and Fabrication work started as per Schedule
2)   PIPING FABRICATION WORK :(INSIDE AND OUTSIDE PIPING PH BUILDING)SCHEDULE ATTACHED IN ANNEXURE 2
  1. All Piping material will reach site by first week of March 2017.(3rd shipment on 12th Feb).
  2. Fabrication work  up to auxiliary Equipment’s and  termination &  pipe line support  will be scheduled after arrival of aux Equipment’s at site.
3)  PIPING FABRICATION & ERECTION WORK: (Steam & Water Piping) SCHEDULED ATTACHED IN ANNEURE 3
  1. All piping materials will reach site by first week of March
  2. Boiler will reach site by 30 April 2017

SEQUENCE

RESPONSIBILITY