ERECTION SCHEDULE

MagnDs

Power

ELECTRICAL AUXILIARY ERECTION

BANCO - PROJECT 3X18.55MW

S.NO

DESCRIPTION

Feb

March

April

May

June

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

AA

ELECTRICAL - Panel Erection

Earthing Outside PHB

11KV VCB Panels

Neutral Grounding Resistance Panel

LT Power Control Center Panel

Battery Charger / UPS Panels & Battery Accessories

AC & UPS Distribution Panel

Generator Control Panel & Common Control Panel

High Voltage Interface Panel

Generator Inter Face Panel & SACOS Panels

Turbo Charger Control Panel

Engine Auxiliary Panel

Common Control Panel

Comon Control Pump House panel

Erection of Station transformer 2 x 2 MVA

BB

ELECTRICAL - Cable Tray Fabrication & Erection

Fabrication of Cable tray Support Structure Inside PHB, Cable Cellar & Control Room

Fabrication of Cable tray Support Structure Inside PHB mechnical Annexure building

Fabrication of Cable tray Support Structure Outside PHB Radiator,Boiler,FTP

Erection of Cable tray Inside PHB, Cable Cellar & Control Room

Erection of Cable tray Mechnical Annexure building

Erection of Cable tray Outside PHB Radiator,Boiler,FTP

CC

ELECTRICAL - Cable Laying & Termination

HT Cable Laying Inside PHB Alternator

HT Cable Laying Outside PHB(Switchyard)& Aux.Transformer

HT Cable Termination Outside PHB(Switchyard)& Aux.Transformer

HT Cable Termination Inside PHB Alternator

LT Power & Control Laying Inside PHB

LT Power & Control Cable Laying Outside PHB

LT Power & Control Cable Termination

Communication Cable Laying

Communication Cable Termination

Note :

1.    The above shedule is based on MAN Equipment arrived at site before 1st week of MAY.

2.    The above schedule is based on all 3 Alternator Alignment before 2nd week of MAY.

3.    The above shedule is based on Switchyard Equipment erection at site before 1st week of April.

4.    The above shedule is based on Tankform Equipment and cables erection at site before 2nd week of MAY.