MAGNUS ELECTRICAL SCHEDULE

 ASSUMPTION: FOB submitted by M/s MDT, Magnus Material transportation 
1) Scheduled Electrical Panel Placement and Leveling based on M/s MDT Auxiliary Equipment ETS
2)  MPPL scope of panels will reach site by first week of April 2017
3)  Cable trays will reach site by First week of March 2017
4)  Civil clearance is required by third week of Feb 2017 to start Cable tray supports Fabrication to meet the attached schedule
5)  Switch yard readiness is required by first week of April 2017
6)   Tank Farm area equipment and instruments should be ready before second week of May 2017

 

 