 CIVIL WORK SCHEDULE 

Work  February 17 March 17 April 17   May 17   Contractor/ Remarks 
  Casting of 1st floor( electrical annex) 20 February 17        MICROMAX
Casting of top floor( electrical annex)   05 March 17       MICROMAX
Chimney foundation ( with curing)  15 February 17         MICROMAX
Radiator foundation ( with curing )  15 February 17         MICROMAX
Substation ( with cable trench )  28 February 17         MICROMAX
Boiler  15 February 17         MICROMAX
 FTP     Civil : 28 February

 Prefab:

10 April 17 

   LABIB & ALAM MARINE
 WTP     30 March 17       LABIB 
 WST     30 March 17       
 DG Structure     20 March 17         Pending drawing
 RFCP Panel room     25 March 17         Pending drawing 
 Pump house     25 March 17         Pending drawing 
 Tank yard DYKE wall     30 March 17         Pending drawing 
 Culvert     30  March 17         Pending drawing 
 Pipe bridge foundation     30  March 17         Pending drawing 
 Pedestal      25 March 17         Pending layout  
 Tower foundation     25 March 17         Pending decison          
 Internal road     30  March 17       
Guard room       25 April 17     Pending design 
 Dranage system       28 April 17     Pending desing 

SEQUENCE